			<title>Council approves $2 million funding of wastewater plant expansion designs</title>
			<link>https://shelburnefreepress.ca/?p=28172</link>
			<pubDate>Mon Aug 24 0:01:09 2026 / +0000  GMT</pubDate>
			<guid isPermaLink="false">https://shelburnefreepress.ca/?p=28172</guid>
			<content-encoded><![CDATA[<!-- wp:paragraph -->
<p>Written By<strong> Paula Brown</strong></p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Local Journalism Initiative Reporter</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>The Town of Shelburne is moving forward with an expansion to its wastewater treatment plant, approving funding for its design.</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Shelburne Town Council, during their meeting on April 26, approved $2 million in funding from the wastewater reserve to finance the design portion of the Water Pollution Control Plant (WPCP) upgrades.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>According to the report to council, the town's wastewater reserve balance at the end of 2020 was $3.4 million with an estimated budgeted transfer of $723,265 added through rates collected. The balance of the sewer reserve is estimated to be $4 million by the end of 2021.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Shelburne's director of finance and treasurer, Carey Holmes said once the design phase is completed and construction commences, the sewer reserve can be replenished from development charges.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>The design work for the expansion is set to begin following the completion of the plant's environmental assessment (EA) study. &nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>“It's about a year design time frame,” said Stephen Burnett, the Town's engineer. “If the EA wraps up mid-summer, this should have the design completed by mid to late summer next year pending any hiccups.”&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>An allocation report of the Water Pollution Control Plant (WPCP) found that there is not sufficient allocation for new and proposed developments. Shelburne Town council received a report in September 2020, which gave the Town three options for upgrading the plant, and estimated the cost of upgrades between $26 million to $34 million.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>The report states, a pilot testing of membrane bioreactors (MBR) water treatment, one of the options given to council for the WPCP expansion, was recently approved by council.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>The WPCP environmental assessment will be finalized pending the “confirmatory results of the pilot study”, which will be completed in the next two months.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Design for the expansion is estimated to require a minimum of one year, while construction will take a minimum of two, following to completion of the design.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>The Town is also undergoing an environmental assessments on the water supply, which has seen issues in servicing and capacity as well.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>In 2020, PW1 or well #1 was taken off-line due to low production. New pumps were installed, rehabilitating the well, but due to air entrainment issues it has remained off-line. Burnett noted they are working on treating the ‘bubbles', which are part of the wells design, installing new equipment, screening, and up to two air release valves.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>“The plan is to have well #1 back online by about mid-summer of 2021,” said Burnett. “If rehabilitation works do not work and we cannot deal with this air entrainment issue then alternatively a new well would potentially be required here, but ultimately [the] prognosis is pretty good.”&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>The Town saw well #3 minimized in use to limit the naturally occurring arsenic levels, which are above the newly reduced drinking water limits, while a new filtration system was being designed. During the wells rehabilitation, it showed signs of being GUDI (groundwater under the direct influence surface water), and taken off-line. Project costs for the well are now estimated at $3 million, up from the originally estimated $1.77 million.</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Work is also being done on PW7 (well #7) and PW8 (well #8), in an attempt to run them together which would double the amount of supply and could increase the flow of PW5 (well #5) and PW6 (well #6) from 75 per cent to 100.&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Burnett added that a source water protect plan would need updating in consultation with the Grand River Conservation Authority (GRCA) and Nottawasaga Valley Conservation Authority (NVCA).&nbsp;</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>“Although most of this information and testing results will be submitted in late spring/early summer it is not anticipated that the approval will be issued until late spring/early summer 2022 for implementation of these improvements,” said Burnett.</p>
<!-- /wp:paragraph -->

<!-- wp:paragraph -->
<p>Burnett said that once the wells are turned back on the Town could meet wastewater demands for more than 15 years, with a new well needed in 2035.&nbsp;</p>
<!-- /wp:paragraph -->]]></content-encoded>
			<excerpt-encoded><![CDATA[]]></excerpt-encoded>
			<wp-post_id>28172</wp-post_id>
			<wp-post_date>2021-05-06 11:12:39</wp-post_date>
			<wp-post_date_gmt>2021-05-06 15:12:39</wp-post_date_gmt>
				</item>
</upm-export>